N

Park News

Read all about it!

27/01/2018

Replacing The Old

The original water main feeding Islawrffordd Holiday Home Park was laid by the 1st and 2nd generation of the Evans family in the early 1960’s.

At that time 1.5” diameter water main seemed adequate. As time has elapsed with the quality and amenities of the holiday homes forever increasing, a decision was made to renew the water main. This involved 600M of 90mm MDPE pipe.

Work commenced on the 4th January with the 3rd and 4th generation of Evans family along with the help of a local ground care contractor and fusion welding specialist. The work was completed by 25th January.

Hoping this will see in the 5th and 6th generation!